Wagga Wagga City Council launched the Wiradjuri Trail Master Plan in August 2021, setting out a 10-year improvement blueprint that includes more than $6 million worth of proposed development.  The aim is to “connect the local community and environment, highlight places of significance to the Wiradjuri and First Nations peoples, and transform the trail into a major tourism asset that will benefit our local economy”.

The Flowerdale Lagoon pedestrian footbridge was one of three high-priority projects identified for the popular 42 km walking track that surrounds the city.

Flowerdale Lagoon existing pedestrian bridge before redesigned and installed by Timber Restoration Services and Wood Research development

The original Flowerdale lagoon bridge to be replaced as a part of council project.

What Was Wagga Wagga Council Looking For?

Wagga Wagga City Council wanted the existing narrow footbridge removed and replaced with the new footbridge in the same alignment and fitting into the existing track, maintaining the same girder soffit RL. Council wanted a bridge that was congruous with the tree-lined anabranch, environmentally and indigenous friendly, in color and shape. With Flowerdale Lagoon often chosen for wedding backgrounds, Council wanted a standout bridge for cyclists, pedestrians and patrons to share. 

Promoting a sustainable, pre-machined, pre-assembled, specially treated engineered glulam timber structure that has a design life of 100 years with little to no maintenance, Council felt the right combination of aesthetics, materials and functionality was in the Timber Rrestoration Services (TRS) proposal.  Being ISO 9000 accredited, Timber Restoration Services provides a quality assured timber structure that Council can have confidence in its long term performance.

The treated engineered glulam side girder superstructure configuration brought together a package of strength, curvature and natural elegance that blended well in the bushland environment of the Flowerdale precinct. The angled handrail and balustrade design naturally guides cyclists to not ride close to balustrading, preventing their pedals from being caught.  A timber top rail of dressed 200Ă—100 hardwood softens the visual presence of galvanised steel posts and balustrading whilst providing a warm natural texture as pedestrians walk along the bridge

Pre assembled design of the new Flowerdale brdige designed by Wood Research and development and Timber Restoration Services.

Treated Engineered Glulam Side Girders with FRP mesh grating.

So why choose treated engineered glulam over other products?

Environmentally, timber has a smaller carbon footprint than reinforced concrete, aluminium, steel and composite fibre.  Once the timber has been cut and treated, the carbon the trees have absorbed during their growth, remains locked in.  Plantation timber is a fast-growing renewable resource and with specialty preservative treatment, will last for 100+ years with a regular maintenance regime.

.

graph depicting CO2 Emissions comparing Engineered Wood to Concrete and Steel

Extracted from “Addressing Embodied Energy with Mass Timber”, S.Zakrzewski & A. Gray
(https://passivehouseaccelerator.com/articles/addressing-embodied-energy-with-mass-timber)

Mass timber, such as engineered glulam, is without question, a highly sustainable product because it requires much less energy to produce than comparable materials, can be recycled without massive energy input and, it sequesters carbon in its fibres.  If it is harvested properly, it is renewable and does not degrade forest ecosystems. Beyond its sustainability benefits, it is also dimensionally stable and allows for precise manufacturing, prefabrication, and quick construction.

Concrete and steel require ongoing regular maintenance particularly for lightweight construction such as footbridges where steel box section trusses and thin concrete slabs are regularly used. Without durable treatments and maintenance, these products will suffer the consequences of moisture penetration, moisture entrapment and corrosion. Hot-dipped galvanising will require major maintenance within 25 years.  The treated preservative glulam that Timber Restoration Services uses requires no coat maintenance.

Timber Restoration Services uses specially preservative treated glulam beams for its bridges that are not available in Australia but is approved by the Australian Pests and Veterinary Medicines Authority.  This heavy oil based preservative treatment doesn’t leach and will provide the durability required from termite and fungal attack.  With substantiated durability tests from the swamps of Louisiana, TRS has the evidence to ratify the 100 year design lifealong with good design and construction practices.

Aesthetically, the natural beauty of timber bridges, nestled in idyllic environments where patrons want to walk and exercise, resonates with local and indigenous communities.  Council concerns of high maintenance and long term durability are nullified through good design and good construction and durable material selection. So why not choose treated engineered glulam over other products?

The Old Deck

Prefabrication

Once the WRD design drawings were finalised and approved by Wagga Wagga City Council, the glulam fabrication shop in Jefferson, Oregon began fabricating the components. Once fabricated and quality checked, the bridge was assembled, then disassembled and sent to the treatment plant. 

With Timber Restoration Services having ISO accreditation, the ISO quality audit before treatment is an important step in achieving the quality standards expected by the clients.  Pre-fabricating the glulam components with holes drilled before treatment means that the special preservative treatment can coat all

Assembled timber bridge supersstructure ready to be sent for treatment by Timber Restoration Services.

Connections are pre-assembled in our plant in Jefferson, Oregon.

Footbridge being assembled in Timber Restoration Services Deception Bay yard
TRS Loading fully assembled and treated Pedestrian Timber bridge for transport to be installed.

The benefit of this method is the quick assembly and construction time.  The treated engineered glulam elements are prefabricated, assembled and disassembled in the workshop prior to being shipped from the US.  Once in TRS’ Queensland yard, the timber structure was then assembled including the FRP mesh decking and balustrading for a final quality audit and ready for transport to site as a complete unit.

A true benefit of treated engineered glulam is that being lightweight, smaller more economical cranes can be used to lift completed treated engineered glulam bridges into position.

This “IKEA” system of bridge building means that there is greater precision and quality control, minimizing of waste on site and errors being made.  With Timber Restoration Services gaining ISO accreditation, this is an important step in achieving the quality audits in place.

Construction

Being recognised as one of nine culturally significant Aboriginal sites around Wagga Wagga, Wiradjuri elder Uncle James Ingram carried out a cultural assessment to check for First Nations artefacts.  Wagga Wagga City Council engaged a Wiradjuri community member with cultural knowledge to monitor excavation works and advise on any finds. As an additional measure, TRS personnel and its subcontractors were required to undertake cultural awareness training conducted by a local Wiradjuri person.

With poor foundation soil quality (silty alluvial clay) and difficult site access for heavy machinery, TRS opted for screw piers as the means to achieve bearing capacity and lateral resistance for the abutments.  2off 178mm dia.x 8.4mm wall thickness screw piers were screwed under each abutment to a depth of 6m.  The heads of the screw piers were then integrated into a concrete pile cap and backwall.  Since the site had strict environmental caveats, limiting tree lopping and clearing, the 8T screw piling excavator was able to easily manoeuvre in position without disturbing tree overhangs.

Timber restoration Services crew screw piling along bank before beginning of installing new bridge.

TRS crews screw piling along banks

Once screw piling was completed, the concrete abutments were formed, inspected, poured on site and left for curing, ready for the bridge.

Flooded abutments

However, a week after the concrete abutments were formed and poured, the site flooded and with ongoing intermittent rain, the bridge installation was delayed. The wet ground conditions from rains and flooding made life difficult in addition to the site’s awkward position made the installation a challenging process.

Coming in from above

Due to its strict environmental caveat, placing a crane close to the bridge site to lift the bridge in was not possible.  A 100 tonne capacity All Terrain mobile crane with a reach of 52m was brought in to lift the 4.8 tonne footbridge directly off the truck, raise it over the tall gum trees that lined the lagoon, before lowering it onto the new concrete abutments. 

TRS Newly designed Flowerdale Lagoon Timber foot bridge lowered in place

123

Compaction of the gravel footpath

Wagga Wagga City Council’s parks and recreation assets officer Rob Owers said, “The footbridge will provide a safe, all-inclusive crossing of the Flowerdale Lagoon, making walking and riding the trail easy and enjoyable for families and other users.  It will increase access for people of all abilities and will also enable cyclists to use this section of the Wiradjuri Trail.”

Mother Nature’s first test

A few weeks post project completion weeks, Flowerdale Lagoon’s newest attraction was subjected to the flooding waters of the Murrumbidgee River and passed its first test of endurance with flying colors.  The Murrumbidgee River at Wagga Wagga peaked at 9.72 meters, causing major flooding in the city for the first time in a decade. The flood waters rose well above the footbridge cycle rail height which is set at 1.4m above the deck level. 

After this event, Timber Restoration Services can confidently say to Mother Nature … “Bring it!”

?Flowerdale lagoon Timber Foot Bridge designed by Wood Research and Development and constructed and installed by Timber Restoration Services.

The Flowerdale Lagoon footbridge, just a few days after flooding in the area subsided.

Flowerdale lagoon Timber Foot Bridge by Wood Research and Development and Timber Restoration Services after flooding.

The Flowerdale Lagoon footbridge, just a few days after flooding in the area subsided.

Regardless of setbacks encountered due to weather and environmental factors. TRS was able to get the bridge installed that will last 100 years and bring great aesthetic value to the Wiradjuri walking Trail. Timber Restoration Services would like to thank the Waga Waga City council for the trust given to us to execute this amazing project. We look forward to working with them potentially in the future on many projects.

Marketing Coordinator – Jacksonville, FL

 

Overview

Are you a student or recent graduate looking for an exciting marketing opportunity to kickstart your career? Timer Restoration Services (TRS) is looking for a motivated, detail-oriented, and creative individual to join our team in the Jacksonville, FL  office and assist in the Marketing department.

 

About the Company

Timber Restoration Services is an industry leader in Timber and Mass Timber construction. We have over 500 completed projects around the world and our proprietary products and methods ensure that your timber structure will last for 100 years.

Our passion for innovation and technology allows us to build fast. strong, and beautiful timber structures that are changing the way the world thinks about construction. We take great pride in every project we complete. Our team works alongside clients from start to finish, providing quality assurance and guidance throughout the entire process. We strive for perfection on each project, always aiming for the highest standards of craftsmanship. With Timber Restoration Services, you can trust that your structure will be built to last.

 

Responsibilities

  • Creating content for internal and external communications such as blogs, newsletters, and organizational charts; developing visual aids and slide decks for presentation purposes; creating graphics for internal and external use.
  • Participating in social media efforts by developing content; scheduling posts; commenting on industry-related topics; sharing relevant company and industry material with our audience. 
  • Managing incoming inquiries on our website and distributing them to the proper department and office.
  • Logging, editing, and organizing marketing collateral resources such as photos, document templates, white pages, and other project narrative materials like case studies.
  • Conducting market research on competitors, including projects, SEO targeting, and backlink-building opportunities.
  • Developing creative concepts for campaigns according to given briefs 
  • Analyzing data from campaigns and sources to create reports that show different KPI metrics such as return on investment (ROI) or cost per acquisition (CPA) cost per click (CPC) etc.
  • Assisting with the coordination and execution of promotional activities such as trade shows, seminars, workshops or events, and other special projects.
  • Other general office duties such as filing, printing, and other tasks as needed.

 

 

Experience and skills We’re looking for

  • The ideal candidate should have excellent communication skills and an eye for graphic design combined with exceptional organizational skills and attention to detail. 
  • Strong knowledge of digital marketing concepts and data analysis is essential for this role along with basic IT proficiency. 
  • Previous experience in a similar position or applied projects would be a bonus but not necessary.
  • Working knowledge: Canva, Photoshop, Illustrator, Technical-blog writing, Google Analytics, and Buffer.

 

 

Compensation

This position is 40 hours a week Monday-Friday 8:30 AM-5:30 PM. ET. The base salary for the role starts at $21.50 -$25.00 an hour with a potential boost in pay depending on experience including applied projects and portfolio if provided.

If you are passionate about digital marketing and learning the ins and outs of how a marketing department runs for an international company then this is an opportunity you won’t want to miss! In return, we offer competitive pay plus the bonus potential of becoming a full-time employee at the end of the internship program.

If this sounds like the perfect job then don’t waste any time applying today!

Job Category: Marketing
Job Type: Full Time
Job Location: Jacksonville FL
 
 
pictured: David Allen the General manager of Timber Restoration Services Canada on a wooded background that is blurred for a professional headshot

David Allen P.eng MBA PMP
General Manager , Canada

 

Drawing upon more than thirty years of project management experience, David adeptly integrates his skills as a seasoned engineer, project manager, and leader across a wide range of project domains. He has successfully delivered complex projects in industries such as oil, gas, space, aerospace, and industrial manufacturing.

Equipped with a master's degree in business and a project management professional designation, David showcases a steadfast commitment to executing projects safely, on time, and within budget while meticulously considering the environmental impact of each project.

Leading a team of skilled professionals with deep expertise in wood structures, David navigates the complexities of managing challenging wood structure construction and restoration projects with both technical proficiency and practical know-how.

 

ST. COLUMBA BELLTOWER-CHARTER TOWERS, QSL, AUSTRALIA

Client: The Roman Catholic Diocese of Townsville
Completion: November 2021

The bell tower at St Columba’s Church is a timber framework set on a concrete base and supports a Burns & Oats bell. It was constructed in 1897 and was believed to be designed by Charles William Smith, the architect of the now-demolished church. St Columba’s church was listed by the National Trust of Queensland in 1973 along with the presbytery and bell tower. The tower is now the only building left from the nineteenth-century complex of buildings on site. It was repaired and painted when the new church was built in 1974 and this may have been when the weatherboards that originally enclosed the
base of the tower as a small shed were removed. WRD was engaged by Townsville Diocese in late 2015 to conduct a condition inspection of the legs of the tower as there was some concern among the congregation regarding these. Subsequent to the Diocese considering the report and sharing it with Heritage Queensland, WRD was then engaged to design the refurbishment and restoration works for the tower.

Following several iterations and the Diocese and Heritage Queensland’s interaction with WRD in the design process, the restoration project was modified to become an exact replica replacement of the tower to support the existing bell and roof system. Under the direction of Heritage Queensland, WRD mimicked each element in the replacement design and has also validated the member capacity under cyclonic wind loadings. Once reconstructed, the bell tower has taken on the persona of the original tower but now can
be expected to last another 100 years or more.

GITLAXT'AAMIKS REC CENTER - CANADA

Client: Allnorth Construction
Completion: June 2022

In July 2020, Wood Research and Development (WRD) was commissioned by
Allnorth Construction to inspect the Gitlaxt’aamiks Recreational Center in
response to concerns raised on the current performance of the glulam rafter
system. A Level II Inspection and Condition Assessment techniques were utilized by WRD in the inspection of the structure to evaluate the current
condition of the upper rafter glulam system. Based on the inspection data, the
Rec Center required a moderate level of refurbishment to enhance the upper
rafters that had delaminated. (This delamination was mostly due to
manufacturing defects). The objective of the recommended repairs is to
improve the structural integrity of the elements inspected and restore the
elements to their original capacity. In addition, the proposed repairs will
provide longevity to the structure, while keeping cost efficiency in mind. A
two-man restoration crew was sent to the project site. The Technicians
installed Retroshear® shear panels to strengthen the glulam girder elements in
all areas of concern and give the roof system many more years of life.

 

WAAJE FIRE TOWER NO.4 -

Client: Queensland Dept. of Housing and Public Works
Completion: December 2020

Located in Queensland, Australia within the Barakula State Forest, Waaje Fire
Lookout Tower majestically stands above the State forest treetops. Initially built in1964 to allow the spotting of fire from the first smoke, the lookout tower was added to the Queensland Heritage Register in January 2018. The Waaje Fire Lookout Tower is a four-legged timber fire tower with a cabin at the top and was built with four 30m single-length grey ironbark poles. It was the first Queensland fire tower to exceed 30 meters in height and is now the tallest surviving intact four-legged timber fire tower. WRD proposed the fire tower needed repairs to the 4 columns as required, repair, replacement, or augmentation of the cross-bracing between the columns, and the installation of anchor blocks and guy wires to reduce the tower’s deflection. The specified restorative works for the lookout cabin, due to the 50-plus years of braving high winds and storm events, consisted of repairs to the louvre frames to return all to a closed position and to install new glass louvres where required, thus again keeping the cabin watertight. To ensure the cabin stayed intact and that future access is restricted, the lowest set of stairs starting at the first lateral tie were also removed.

 

PENTICTON MEMORIAL ARENA RESTORATION - PENTICTON, BC, CANADA

Client: 
Completion: 

The Penticton Memorial Arena is a 2,212-seat multi-purpose arena in Penticton, British Columbia. It has hosted several decades of hockey, and figure skating events, training camps, and various dry-floor sporting and entertainment events. It continues to serve as a significant ice surface for local minor hockey teams, the Okanagan Hockey School, and many recreational leagues.

As a popular and long-standing sports arena, it is critical the structure is preserved to continue as a much-loved center for sports gatherings. TRS was able to restore the arches in the arena and preserve them against decay to ensure the arena is here for a long time.

DUNWOODY COUNTRY CLUB - ATLANTA, GA, USA

Client: Dunwoody Country Club
Completion: December 2022

The Dunwoody Country Club is a vibrant and exclusive private country club. Dunwoody boasts a variety of recreational facilities and dining services for members, guests, and families. The men’s lounge in the club had just been updated and renovated when the roof support system and its truss and other supporting members were inspected and it was discovered they were failing.

After inspections were carried out by Wood Research and Development (WRD), TRS was brought in and hired to restore the roof truss system and support members. These repairs were completed by our experienced technicians and ended up preventing the client from spending nearly $1 million dollars. 

 

"THE NEST" AT ROBINSON PRESERVE - BRADENTON, FL, USA

Client: 
Completion:

The Nest is a unique recreational building within the Robinson Preserve in Manatee County, FL shaped to represent a bird’s nest. As the roof rafters and floor beams extend out past the building envelope, moisture wreaked havoc on the ends of the timber elements.

Glulam beams were procured from the Southeastern US to match the species already in the structure. We then manufactured the required beam lengths in the shop. This restoration required removing the existing damaged wood and installing new joists. To save costs in materials and installation, only the ends of the joists were to be removed. We used a mortise and tenon connection to attach the new joists to the existing elements. The end result was a structurally sound timber connection that was not visible from the outside.

HERITAGE WALKWAY BRIDGE - WEST GRAY, ON

Client: Municipality of West Gray
Completion: December 2018

The original structures was in use by the Canadian Pacific Railway Company for many years, with the last train passing over the bridge in 1985. Many local patrons and tourists use this bridge to cross over or stop to look at the beautiful views of the river and the falls over the dam. The bridge is 75.3m long and was required to conform to the current codes and practices and in keeping with the heritage theme. Large portions of the sub and superstructure appeared to be in poor shape.  Based on this information Engineering recommended replacement of the caps, superstructure, deck and railings onto the existing piles.  Our method of using the EPHOD® Stress Time Wave system would have picked up the pile decay before any engineering recommendations were made, which would have resulted in a savings to the client. This added expense to the project and was a disappointment to the client who understood that this was a necessary extra cost to make this project a success.

FLOWERDALE LAGOON PEDESTRIAN BRDGE WAGA WAGA, NSW AUSTRALIA

Client: Waga Waga City Council
Completion: September 2022

Wagga Wagga City Council launched the Wiradjuri Trail Master Plan in August 2021, setting out a 10-year improvement blueprint that includes more than $6 million worth of proposed development.  The aim is to “connect the local community and environment, highlight places of significance to the Wiradjuri and First Nations peoples, and transform the trail into a major tourism asset that will benefit our local economy”. The Flowerdale Lagoon pedestrian footbridge was one of three high-priority projects identified for the popular 42 km walking track that surrounds the city.

Promoting a sustainable, pre-machined, pre-assembled, specially treated engineered glulam timber structure that has a design life of 100 years with little to no maintenance, Council felt the right combination of aesthetics, materials and functionality was in the Timber Restoration Services (TRS) proposal.  Being ISO 9000 accredited, TRS provides a quality assured timber structure that Council can have confidence in its long term performance. The treated engineered glulam side girder superstructure configuration brought together a package of strength, curvature and natural elegance that blended well in the bushland environment of the Flowerdale precinct. The angled handrail and balustrade design naturally guides cyclists to not ride close to balustrading, preventing their pedals from being caught.  A timber top rail of dressed 200×100 hardwood softens the visual presence of galvanised steel posts and balustrading whilst providing a warm natural texture as pedestrians walk along the bridge

JIMMY GULLY PEDESTRIAN BRIDGE HARLIN, QLD, AUSTRALIA

Client: Somerset Regional Council
Completed: June 2018

Jimmy Gully Pedestrian Bridge crosses Jimmy Gully along the Brisbane Valley Rail Trail (BVRT) near Harlin, Queensland. Jimmy Gully Bridge was a 6 span timber railway bridge that was decommissioned in the early 1990’s. Each span consisted of three girder lines with the two middle spans comprised of double stacked hardwood log girders. Each pile bent has three hardwood timber piles with the middle two bents consisting of five piles with the outer (batter) pile on each side providing lateral stability to the structure.

An extensive inspection of Jimmy Gully Bridge was completed by Wood Research and Development (WRD) technicians on 24 May 2016. The aim of the inspection was to complete the visual and EPHOD® (Electronic Pulse Highlight and Outline Diagnostic) compression wave technology analysis of the in-situ condition of the major structural elements of the bridge. The design of any restoration refurbishment, upgrade and repair strategies was then taken into account based on the inspection data collected.

MANNUS CREEK BRIDGE #9 NSW, AUSTRALIA

Client: Snowy Valley Regional Council
Completion: December 2019

 

Snowy Valley Regional Council recognised the growing trend and applied for NSW Government’s Restart NSW Regional Tourism Infrastructure fund and Stronger Communities grants.  Through this funding, the 21km Tumbarumba to Rosewood Rail Trail, a walking and cycling trail that runs through a non-operational railway corridor, became the pilot for the State and a working model for future New South Wales rail trails.

For more information, see our blog post on this project.

MCGILLVRAY FOREST SERVICE ROAD BRIDGE (K162) - SUN PEAKS, BRITISH COLUMBIA, CANADA

Client: Ministry of Forests, Lands, Natural Resource Operations and Rural Development (FLNRORD)
Completion: July 3, 2019

 

This glulam all-timber bridge is 21.2m long, spans 20.6m an has a 5.5m deck.  The bridge sits on a 2 percent grade and has a 20-degree skew.

This resource road bridge is designed for an L100 loading and comprises five Douglas Fir glulam girders reinforced with aramid fibers for shear and bending.  These are overlain by a glulam subdeck and solid running planks.

This bridge was designed, fabricated/preassembled off-site and reassembled on-site, as a demonstration of what is possible for timber bridges in British Columbia.

SUGARLOAF ROAD BRIDGE, AXEDALE, CENTRAL VICTORIA, AUSTRALIA

Client: City of Greater Bendigo
Completion: October 12, 2019

Timber Restoration Systems has this week commenced work on Sugarloaf Road Bridge in Axedale, Central Victoria.

Work includes replacing log girders, driving new piles, repairing old piles, and installing a new transverse deck.  The bridge will be closed for the period of the works.

OGER BACON BRIDGE - AMHERST, NOVA SCOTIA, CANADA

Client: Nova Scotia Department of Transportation and Infrastructure Renewal
Completion: December 22, 2019

Timber Restoration Services (TRS) was awarded the contract to produce a
design/build bridge to replace the existing 48-year-old steel arch bridge
just outside of Amherst, NS. Located in the highest embedded and exposed
corrosion zone in Canada, many elements of the bridge were rusted out
and failed. The bridge was taken out of service and slated for replacement
in 2017. TRS contracted Wood Research and Development (WRD), to
design a unique state-of-the-art timber bridge. Due to the uniqueness of
this bridge, WRD was also responsible for construction oversight for the
project. WRD’s first step in the design work for this project was to test the
existing 80-year-old timber piles used in the old bridge.

TRS  manufactured the bridge in our state-of-the-art plant in Jefferson, Oregon with the aid of several Canadian technicians who spent three months in Jefferson to aid in the construction of this bridge. The bridge components were shipped to the project site in
25 tractor-trailer loads. The structure consists of two 12-meter jump spans and a 39-meter three-pinned glulam timber arch. The design included the placement of the arch span using a 500-tonne crane, sitting on one of the jump spans, with a smaller crane on the opposite jump span helping guide the arch in place.

DELEGATE RIVER BRIDGE UPGRADE - DELEGATE, NSW, AUSTRALIA

Client: Snowy Monaro Regional Council
Completion: September 9, 2020

TRS entered into a contract with Snowey Monsaro Council in June of 2020, to carry out repair upgrades to the Delegate River Bridge. The upgraded design is based on a Level 2 inspection and condition report that was carried out in 2018.

The work done on the bridge was comprised of constructing a new sill beam foundation, as well as the fabrication of two new frame bents. Our certified timber technicians also completed pile repairs, and the replacement of six corbels, as well as sixteen girders. A significant portion of the deck was renewed as well.

SOUTH ARM BRIDGE UPGRADE - BRUNSWICK HEADS, NSW, AUSTRALIA

Client: Byron Shire Council
Completion: October 2020

Timber Restoration Services (TRS) won the contract to upgrade the 63m bridge from 10-tonne to 44-tonne traffic loading. As part of the rehabilitation process, TRS recycles the existing timbers where possible and reuses the log timbers at the Council stockyard.

To ensure the recycled timber receives the best protection, TRS applies Copper Naphthenate Oil Emulsion (CN oil) and uses a paraffin-based sealant, Anchorseal®, to seal the cuts. The cuts are treated with Decaystop®, borate salt rods, to inhibit fungi growth and maintain easy access to the bridge elements.

Laborers – Caboolture, AUS

 

About the Company

Since 2005, Timber Restoration Services (TRS) have been building and restoring timber structures in the USA, Canada, and Australia.  We have an immediate need for Labourers who have some experience in the carpentry field such as carpenter helpers. Must have knowledge of power and hand tools.

 

About the Role

The individual would have on-the-job training to become a Level II Inspection, Retrofit, and New Structures Technician.

TRS is currently filling positions for our  Australian divisions so if you like to travel this is a great opportunity to see Australia close up and get paid to go.

Responsibilities

Successful applicants must be able to pass and/or possess the following:

  • Willing and able to travel; be on the road for up to 3 months at a time
  • Must have a valid driver’s license
  • Have a current and valid passport or the ability to obtain one
  • Must pass a criminal background check and pre-employment drug/alcohol testing
  • Willing/able to work in all weather conditions
  • Willing/able to work at heights from ladders, scaffolding, elevated work platforms, etc.…
  • Trustworthy and of good character, reliable and punctual
  • Undergo randomize drug testing and breathalyzer on job sites due to heavy equipment and tools

Other beneficial skills/experience:

  • Knowledge and prior use of shop tools
  • Construction work
  • Small equipment such as mini-ex, skid steer
  • Able to read blueprints

 

 

Benefits and Compensation

  • Above-average pay rate
  • Company pension and profit-sharing
  • A medical plan including dental, vision, prescription drugs, extended health care, disability, and life insurance

All candidates are required to complete pre-employment screenings, which include a background check, driver’s license check, and drug screening.

Job Category: Construction
Job Type: Full Time
Job Location: Caboolture AUS
 

Marketing Coordinator – Jacksonville, FL

 

Overview

Are you a student or recent graduate looking for an exciting marketing opportunity to kickstart your career? Timer Restoration Services (TRS) is looking for a motivated, detail-oriented, and creative individual to join our team in the Jacksonville, FL  office and assist in the Marketing department.

 

About the Company

Timber Restoration Services is an industry leader in Timber and Mass Timber construction. We have over 500 completed projects around the world and our proprietary products and methods ensure that your timber structure will last for 100 years.

Our passion for innovation and technology allows us to build fast. strong, and beautiful timber structures that are changing the way the world thinks about construction. We take great pride in every project we complete. Our team works alongside clients from start to finish, providing quality assurance and guidance throughout the entire process. We strive for perfection on each project, always aiming for the highest standards of craftsmanship. With Timber Restoration Services, you can trust that your structure will be built to last.

 

Responsibilities

  • Creating content for internal and external communications such as blogs, newsletters, and organizational charts; developing visual aids and slide decks for presentation purposes; creating graphics for internal and external use.
  • Participating in social media efforts by developing content; scheduling posts; commenting on industry-related topics; sharing relevant company and industry material with our audience. 
  • Managing incoming inquiries on our website and distributing them to the proper department and office.
  • Logging, editing, and organizing marketing collateral resources such as photos, document templates, white pages, and other project narrative materials like case studies.
  • Conducting market research on competitors, including projects, SEO targeting, and backlink-building opportunities.
  • Developing creative concepts for campaigns according to given briefs 
  • Analyzing data from campaigns and sources to create reports that show different KPI metrics such as return on investment (ROI) or cost per acquisition (CPA) cost per click (CPC) etc.
  • Assisting with the coordination and execution of promotional activities such as trade shows, seminars, workshops or events, and other special projects.
  • Other general office duties such as filing, printing, and other tasks as needed.

 

 

Experience and skills We’re looking for

  • The ideal candidate should have excellent communication skills and an eye for graphic design combined with exceptional organizational skills and attention to detail. 
  • Strong knowledge of digital marketing concepts and data analysis is essential for this role along with basic IT proficiency. 
  • Previous experience in a similar position or applied projects would be a bonus but not necessary.
  • Working knowledge: Canva, Photoshop, Illustrator, Technical-blog writing, Google Analytics, and Buffer.

 

 

Compensation

The position is designated as an internship, for upcoming graduates. This position is 40 hours a week Monday-Friday 8:30 AM-5:30 PM. ET. The base salary for the role starts at $19.50 -$21.00 an hour with a potential boost in pay depending on experience including applied projects and portfolio if provided.

If you are passionate about digital marketing and learning the ins and outs of how a marketing department runs for an international company then this is an opportunity you won’t want to miss! In return, we offer competitive pay plus the bonus potential of becoming a full-time employee at the end of the internship program.

If this sounds like the perfect job then don’t waste any time applying today!

Job Category: Marketing
Job Type: Full Time
Job Location: Jacksonville FL
 

DAVIDE MAGGIOLO

With over 30 years specializing in technical timber advice and engineered wood products, Davide has established his credentials as a timber expert.

Davide has worked alongside multiple field crews to learn the process of constructing timber boardwalks and bridges.

Working as a project manager and contract administrator for multiple builders on different projects, Davide supports the engineers and field crews with technical and construction advice.

PATRICK BIGG
General Manager, Australia

As the General Manager for TRS Australia, Pat’s leadership skills come to the fore, mentoring new engineers and technicians as well as managing field crews stationed at projects throughout Australia.

Pat is a structural bridge and timber engineer, his expert knowledge, experience, and position allows him the freedom to oversee design and operations but also to provide structural support when needed.